Screening request for a 450MW Battery Energy Storage System submitted to The Consents Unit
May 2022
Expected Consents Unit response to Screening request.
August 2022
Pre Application Consultation with Community held at Alyth Town Hall.
August 2022
Screening Response - Non EIA Development
October 2022
Submission of Application
December 2022